The AI CapEx Trade Is Changing: From Picks-and-Shovels to Power

Nvidia was the obvious AI trade. The non-obvious one is whoever plugs the grid into the building. Hyperscalers are guiding to $725 billion of 2026 capex, and the binding constraint is no longer chips. It's turbines, transformers, and interconnection queues.

Tech Talk News Editorial12 min readUpdated Jul 14, 2026
ShareXLinkedInRedditEmail
The AI CapEx Trade Is Changing: From Picks-and-Shovels to Power

Key takeaways

  • Google, Amazon, Microsoft and Meta are collectively guiding to roughly $725 billion in 2026 capital expenditures, up about 77% from around $410 billion the prior year.
  • GE Vernova's gas turbine backlog hit 100 GW in Q1 2026, but its factories can only build about 10 GW a year through 2030, so demand is now capped by factory throughput, not by orders.
  • In PJM Interconnection the wait from interconnection application to commercial operation rose from under two years in 2008 to over eight years in 2025, and high-power transformer lead times now stretch to about five years.
  • Over the trailing year GE Vernova returned about 125% and Vertiv about 154%, versus Nvidia's roughly 36% gain in 2025, so the power-infrastructure names have outrun the chip trade.
  • The IEA projects global data center electricity use to roughly double from about 415 TWh in 2024 to around 945 TWh by 2030, and worldwide data-center power demand rises about 27% in 2026 to roughly 132 GW.

For three years the AI trade had one name on the marquee. You bought Nvidia, you understood that every model everyone was building ran on its silicon, and you were right. That was the obvious trade, and obvious trades work until the whole market is standing on the same side of the boat.

Here is the thing about a compute boom that nobody put on a slide in 2023. A GPU is useless until it has power. Not “power” in the abstract sense of a wall socket, but hundreds of megawatts of firm, always-on electricity, delivered to a specific building, through a substation that has to be built, connected to a grid that has to agree to carry the load. You can order a rack of H-series chips and have it in weeks. You cannot conjure the interconnection in weeks. In some markets you cannot conjure it in five years.

That gap, between how fast you can buy compute and how slowly you can energize it, is the whole investing thesis here. The bottleneck moved. It used to be chips. Now it is watts. And the companies that sell the watts, the turbines that make them, and the copper that carries them have quietly become the best-performing part of the entire AI complex.

~$725B
Big-four hyperscaler 2026 capex guidance, up ~77% YoY
100 GW
GE Vernova gas turbine backlog, Q1 2026, vs ~10 GW/yr build capacity
8+ years
PJM interconnection wait, up from under 2 years in 2008
+154% / +125%
Trailing-year return: Vertiv / GE Vernova, vs Nvidia +36% in 2025

The money is real, and it is enormous

Start with the demand signal, because it is not subtle. Google, Amazon, Microsoft and Meta are collectively guiding to roughly $725 billion in capital expenditures for 2026. That is up about 77% from around $410 billion the year before. Amazon sits near $200 billion, Google near $185 billion, Meta at $125 billion to $145 billion, and Microsoft around $120 billion. Four companies. Three-quarters of a trillion dollars. In one year.

A 77% jump in capex is not a maintenance budget. It is four of the most disciplined capital allocators on earth deciding, simultaneously, that the risk of underbuilding AI capacity is worse than the risk of overbuilding it. You can debate whether they are right. What you cannot debate is where the money physically goes. A data center is not mostly chips by cost once you count the shell, the power, and the cooling. And the part that has become impossible to buy off the shelf is the part that turns a field into a live megawatt.

Plain English

The picks-and-shovels trade was always about selling gear to the gold rush instead of panning yourself. Nvidia was the pick. But the mine has flooded, and now the scarce thing is the pump. Power is the pump.

Why watts, not chips, is the binding constraint

Here is the number that reframes everything. In PJM Interconnection, the largest grid operator in the US, the average time from filing an interconnection application to reaching commercial operation rose from under two years in 2008 to over eight years in 2025. Eight years. For an industry that reprices its entire hardware stack every eighteen months, an eight-year queue for the electricity to run it is not a delay. It is a wall.

And it is not just the queue. The physical gear has its own backlog. Substation transformer lead times now exceed 160 weeks, over three years, up from about 140 weeks in 2023. High-power transformers that took 24 to 30 months before 2020 now stretch to about five years. AI infrastructure projects that entered service in 2025 averaged more than seven years to reach operational status. You do not solve a seven-year timeline by writing a bigger check to TSMC.

You can buy a GPU faster than you can energize the building it goes in. That single asymmetry is the entire second-derivative trade.

This is the part the market took a while to price. Everyone understood that AI needed a lot of electricity. Fewer people understood that the supply chain for delivering that electricity, the turbines and transformers and switchgear and the humans who install them, has a multi-year lead time and cannot be scaled by throwing money at it in a single quarter. When demand is capped by factory throughput instead of by orders, the manufacturer gets pricing power. That is the setup you want to own.

The turbine maker who ran out of factory

GE Vernova is the clearest expression of the thesis. Its gas turbine backlog reached 100 GW in Q1 2026, up from 83 GW at the end of 2025, and it guides to at least 110 GW of combined backlog and slot reservations by year-end. About 20 GW of that, roughly a fifth, is tied directly to data centers and AI.

Now here is the punchline. GE Vernova can only manufacture roughly 10 GW of gas turbines a year through 2030. It is targeting about 24 GW of annual capacity by 2028, but until then, demand is not the problem. The factory is. A 100 GW backlog against a 10 GW annual build rate is a multi-year delivery queue where customers are lining up for slots that do not exist yet. When that happens, you raise prices. CEO Scott Strazik said 2026 orders would be priced 10 to 20 points higher than Q4 2025 orders. That is what scarcity looks like on an income statement.

The electrical side tells the same story. GE Vernova's Electrification segment booked $2.4 billion in data-center equipment orders in Q1 2026 alone, which exceeded its entire 2025 total for that category. It shipped 25 gas turbines in the quarter, a 32% year-over-year increase. This is not a company hoping AI shows up. This is a company that cannot build fast enough to serve the AI that already showed up.

Why this matters

A backlog you cannot fill for years is a different animal than a hot order book. It de-risks the next several years of revenue and it hands the seller pricing power on every new slot. That combination, visible multi-year revenue plus rising prices, is rare, and it is exactly what the power-infrastructure names have right now.

Inside the building: cooling, switchgear, and copper

The turbine makes the power. Something has to distribute it, condition it, and keep the racks from cooking. That is where Vertiv and Eaton live, and their numbers are, if anything, louder than GE Vernova's.

Eaton's data-center orders accelerated roughly 200% in Q4 2025, with sales up over 40% year-over-year, and its data-center backlog is described as equal to about eleven years of 2025 construction. Read that again. Eleven years of backlog. Vertiv's organic orders grew 81%, and Q1 2026 revenue rose 30% year-over-year. These are the companies selling the power distribution units, the busways, the liquid cooling, the uninterruptible power systems. The unglamorous guts of the room.

Then there is Quanta Services, which is the labor and construction layer, the people who actually build the grid connections and the electrification work. Quanta posted Q1 2026 adjusted EPS of $2.68 against $2.03 expected, on revenue of $7.87 billion, up about 26%, with a record $48.5 billion backlog driven by grid and electrification work. When you cannot find enough qualified crews to string the wire, the company that has the crews becomes a chokepoint too.

Takeaway

Four names, four layers of the same wall: GE Vernova makes the power, Eaton and Vertiv move and condition it inside the building, Quanta connects it to the grid. Every one of them is running a backlog measured in years, not quarters. That is what a supply-constrained boom looks like from the seller's side.

The demand curve is not slowing down

If you think this is a one-year spike, the forecasts disagree hard. The IEA projects global data center electricity consumption to roughly double from about 415 TWh in 2024 to around 945 TWh by 2030 in its base case, with electricity consumption from AI-focused data centers rising about 50% in 2025 alone. In the US specifically, data centers account for around half of the total projected electricity demand increase through 2030. Half of the entire country's demand growth, from server rooms.

On the power side, worldwide data center demand is projected to rise about 27% in 2026 to roughly 132 GW, up from 104 GW in 2025, and to reach about 290 GW by 2030. Bloom Energy's January 2026 report estimates US data center demand nearly doubling from 80 GW in 2025 to 150 GW by 2028. Goldman Sachs projects global data center power demand up about 165% from 2023 levels by 2030, and one estimate cited in April 2026 pegs AI data-center electrification alone at about $1.4 trillion of needed investment by 2030.

Different forecasters, different methods, same direction and same rough magnitude: the electricity demand from this buildout roughly doubles by the end of the decade. When the demand side is that durable and the supply side has a multi-year lead time, the squeeze does not resolve quickly. It compounds.

Nuclear is the tell

Want to know how desperate the hyperscalers are for firm power? Watch where they are willing to go. Meta signed nuclear agreements in January 2026 with Oklo, Vistra and TerraPower for up to 6.6 GW by 2035, including a 20-year Vistra power purchase agreement for over 2,600 MW and a 1.2 GW Oklo campus in Pike County, Ohio. As of May 2026, every major hyperscaler had signed at least one nuclear deal, with 13 announced projects committing over 9.8 GW.

Nuclear is slow, capital-heavy, and politically fraught. Companies do not sign 20-year nuclear PPAs because it is convenient. They sign them because they have looked at the grid queue, looked at their own load growth, and concluded that waiting for the utility to catch up is not an option. When the buyers of power start underwriting their own reactors, that is not a sentiment indicator. That is a company telling you, with its balance sheet, that firm electricity is the scarce input.

Context

A power purchase agreement is a long-term contract to buy electricity at a set price from a specific generator. Hyperscalers signing 20-year PPAs are effectively pre-buying decades of supply because they do not trust the open market to have it available when they need it.

The scoreboard already agrees with me

Here is where the thesis stops being a story and becomes a number. Over the trailing year, GE Vernova returned about 125% and Vertiv about 154%. Year-to-date in 2026, GE Vernova was up about 74% and Vertiv about 92%. Nvidia gained roughly 36% in 2025. The picks-and- shovels play on the chip got beaten, badly, by the picks-and-shovels play on the power.

I am not telling you Nvidia is a bad company. It is an extraordinary one, and it still sells the single most important component in the stack. But the market has largely figured out the chip. Thirty analysts cover it, every fund owns it, the story is fully priced. The edge in investing is rarely in the obvious layer once the obvious layer is on the cover of every magazine. The edge is one derivative out, in the layer that is structurally scarce and less crowded.

The chip was the first-order trade. The power to run the chip is the second-order trade, and second-order trades are where the crowd hasn't finished arriving.

How I'd think about the risk

None of this is a free lunch, and I would be doing you a disservice to pretend the setup has no downside. These stocks have already run hard. A 154% year means a lot of the good news is in the price, and names that trade on backlog and forward demand get punished violently the moment growth expectations wobble. If the hyperscalers ever blink on capex, if $725 billion turns out to be a peak rather than a way station, the power names fall faster than the market because their multiples assume the spending continues.

The way I frame it: the demand is real and the supply constraint is real, but the valuations already reflect a good chunk of both. This is not the trade you make because it is cheap. It is the trade you make because the constraint is structural and multi-year, and because the thing being sold, delivered electricity, is the one input in the AI stack that money genuinely cannot accelerate past a certain point. Transformers take five years whether you are Microsoft or a machine shop.

So watch the capex guidance, because that is the demand tap and the hyperscalers control it. Watch the backlogs, because a backlog that stops growing is the first sign the squeeze is easing. And watch the interconnection queues and the transformer lead times, because as long as those stay measured in years, the companies that supply the watts keep the pricing power. The obvious trade was the chip. The one worth studying now is whoever plugs the grid into the building.

Sources and further reading

  1. 1.PrimaryInternational Energy Agency, "Electricity 2026," Executive Summary. Global data center electricity consumption projected to roughly double from about 415 TWh in 2024 to around 945 TWh by 2030 in the base case.
  2. 2.PrimaryInternational Energy Agency, "Electricity 2026," Demand. AI-focused data center electricity consumption rising about 50% in 2025; US data centers account for around half of projected demand growth through 2030.
  3. 3.PrimaryGE Vernova Inc., Form 8-K, Q1 FY2026 (SEC). Gas turbine backlog of 100 GW, guidance to at least 110 GW combined backlog and slot reservations, 10 GW annual build capacity through 2030, 24 GW capacity target by 2028, 25 turbines shipped in the quarter.
  4. 4.Reportingmgrid.org, "GE Vernova’s gas turbine backlog hits 100 GW as data centers drive $2.4B in Q1 orders". April 22, 2026. About 20 GW of backlog tied to data centers, $2.4B in Q1 Electrification data-center orders, 10 to 20 point price increase on 2026 orders per CEO Scott Strazik.
  5. 5.ReportingUtility Dive, "Meta inks nuclear deals for up to 6.6 GW from Oklo, Vistra, TerraPower". January 2026. Up to 6.6 GW by 2035, 20-year Vistra PPA for over 2,600 MW, 1.2 GW Oklo campus in Pike County, Ohio; over 9.8 GW of hyperscaler nuclear deals as of May 2026.
  6. 6.ReportingData Center Knowledge, "Why AI Data Center Projects Face Years of Delays After Approval". Transformer lead times exceeding 160 weeks, high-power transformers stretching to about five years, PJM interconnection wait rising from under 2 years in 2008 to over 8 years in 2025, projects averaging over seven years to operational status.
  7. 7.ReportingTom's Hardware, "Big Tech's AI spending plans reach $725 billion". February 2026. Collective 2026 capex guidance of roughly $725 billion, up about 77% from around $410 billion, with per-company breakdown.
  8. 8.ReportingForeign Policy Journal, "Vertiv (VRT) and GE Vernova (GEV) Positioned To Beat The Market As Power Demand Surges". July 13, 2026. Vertiv organic orders up 81%, Q1 2026 revenue up 30%; Eaton orders up ~200% in Q4 2025; worldwide data-center power demand rising ~27% in 2026 to ~132 GW and to ~290 GW by 2030.
  9. 9.DataPortfoliosLab, GEV vs VRT Performance Comparison. Trailing-year returns of about 125% for GE Vernova and about 154% for Vertiv; year-to-date 2026 gains of about 74% and 92% respectively.
  10. 10.ReportingGartner, "Data Center Electricity Consumption to Grow 26% in 2026". June 10, 2026. Corroborates the pace of data-center electricity demand growth in 2026.

Frequently asked questions

What is the AI capex trade in 2026 and how has it changed?
The AI capex trade in 2026 has shifted from chips to power. The four biggest hyperscalers are guiding to roughly $725 billion in 2026 capital spending, and the binding constraint on building data centers is no longer GPU supply but electricity: turbines, transformers, and grid interconnection. That has pushed power-infrastructure names like GE Vernova and Vertiv ahead of Nvidia's stock performance.
Why is power the bottleneck for AI data centers instead of chips?
Power is the bottleneck because you can buy GPUs faster than you can energize a building. In PJM the wait from interconnection application to commercial operation has climbed from under two years in 2008 to over eight years in 2025, substation transformer lead times exceed 160 weeks, and high-power transformers now take about five years. Chips ship in weeks; the grid connection takes years.
How much are the big four hyperscalers spending on capex in 2026?
Google, Amazon, Microsoft and Meta are collectively guiding to roughly $725 billion in 2026 capital expenditures, up about 77% from around $410 billion the year before. Amazon is near $200 billion, Google near $185 billion, Meta at $125 billion to $145 billion, and Microsoft around $120 billion.
Which power-infrastructure stocks are tied to the AI buildout?
The main power-infrastructure names tied to the AI buildout are GE Vernova, Vertiv, Eaton and Quanta Services. GE Vernova makes the gas turbines, Vertiv and Eaton make the electrical and cooling gear inside the data center, and Quanta Services builds the grid connections. Over the trailing year GE Vernova returned about 125% and Vertiv about 154%, versus Nvidia's roughly 36% gain in 2025.
Why are hyperscalers signing nuclear power deals?
Hyperscalers are signing nuclear deals because they need enormous, always-on power and the grid cannot deliver it fast enough. Meta signed agreements in January 2026 with Oklo, Vistra and TerraPower for up to 6.6 GW by 2035, and as of May 2026 every major hyperscaler had signed at least one nuclear deal, with 13 announced projects committing over 9.8 GW.
How much will data center electricity demand grow by 2030?
The IEA projects global data center electricity consumption to roughly double from about 415 TWh in 2024 to around 945 TWh by 2030 in its base case. Worldwide data-center power demand is projected to rise about 27% in 2026 to roughly 132 GW and reach about 290 GW by 2030, and Goldman Sachs projects global data center power demand up about 165% from 2023 levels by 2030.

Written by

Tech Talk News Editorial

Computer engineering background. Writes about software, AI, markets, and real estate, and the places where the three meet.

More about the author
ShareXLinkedInRedditEmail